Milestone calendar

From R3levees

Jump to: navigation, search


PAL Workflow Milestones

SundayMondayTuesdayWednesdayThursdayFridaySaturday
28
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
1
2
3


New Milestone

PAL workflow event:

Upcoming PAL Milestones

The following timeline shows up to the next 25 milestone events

Effective date PAL milestone Hydraulic system Event PAL Letter Date
Chester Creek Levee System 1-Year Progress Report Due 1269057600March 20, 2010 Levee owner progress report due Chester Project
Plymouth System PAL Agreement Due 1271131200April 13, 2010 Levee owner response due Plymouth System
Wilkes-Barre-Hanover Township Levee System PAL Agreement Due 1271131200April 13, 2010 Levee owner response due Wilkes-Barre-Hanover Township System
Elkins Levee System 1-Year Progress Report Due 1271476800April 17, 2010 Levee owner progress report due Elkins Project
Spring Creek Levee maintenance deficiency correction data due 1273204800May 7, 2010 Levee owner maintenance deficiency correction data due Spring Creek Project
Left Bank Four Mile Run Levee System Compliance By 1273204800May 7, 2010 Levee owner maintenance deficiency correction data due Four Mile Run Project
Right Bank Four Mile Run Levee System Compliance By 1273204800May 7, 2010 Levee owner maintenance deficiency correction data due Four Mile Run Project
Spring Creek Levee System Compliance By 1273204800May 7, 2010 Levee owner maintenance deficiency correction data due Spring Creek Project
Norfolk Floodwall Levee System Compliance By 1273204800May 7, 2010 Levee owner maintenance deficiency correction data due Norfolk Floodwall, VA Project
Duryea Levee System PAL Agreement Due 1273636800May 12, 2010 Levee owner response due Duryea Project
Wilkes-Barre-Mill Creek Levee System PAL Agreement Due 1273636800May 12, 2010 Levee owner response due Wilkes-Barre-Mill Creek Project
Howard Levee System Compliance By 1275537600June 3, 2010 Levee owner maintenance deficiency correction data due Foster Joseph Sayers Project
Kitzmiller Levee System 1-Year Progress Report Due 1277179200June 22, 2010 Levee owner progress report due Kitzmiller Project
Blaine Levee System 1-Year Progress Report Due 1277179200June 22, 2010 Levee owner progress report due Blaine Project
East & West Ridgeley Levee System 1-Year Progress Report Due 1277179200June 22, 2010 Levee owner progress report due Ridgeley Project
Painters Mill Flood Dike Compliance By 1277438400June 25, 2010 Levee owner maintenance deficiency correction data due Painters Mill Flood Dike Project
Left Bank of Codurus Creek Levee System Compliance By 1277870400June 30, 2010 Levee owner maintenance deficiency correction data due York Project
Tyler Run Floodwall Levee System Compliance By 1277870400June 30, 2010 Levee owner maintenance deficiency correction data due York Project
Right Bank of Codurus Creek Levee Compliance By 1277870400June 30, 2010 Levee owner maintenance deficiency correction data due York Project
North Moorefield Levee System Compliance By 1284782400September 18, 2010 Levee owner maintenance deficiency correction data due Moorefield Project
East Bayard Levee System Compliance By 1284782400September 18, 2010 Levee owner maintenance deficiency correction data due Bayard Project
West Bayard Levee System Compliance By 1284782400September 18, 2010 Levee owner maintenance deficiency correction data due Bayard Project
South Petersburg Levee System Compliance By 1284782400September 18, 2010 Levee owner maintenance deficiency correction data due Petersburg Project
South Moorefield Levee System Compliance By 1284782400September 18, 2010 Levee owner maintenance deficiency correction data due Moorefield Project
North Petersburg Levee System Compliance By 1284782400September 18, 2010 Levee owner maintenance deficiency correction data due Petersburg Project
… further results


PAL Milestones: Timeline View

The timeline visualizes R3Levee milestones in a linear fashion using MIT Simile Project's Timeline. The graph initially centers on today's date, with past events to the left and upcoming events to the right. The graph's upper section delimits time on a weekly scale while the lower section is monthly. You may click and drag either section to observe past and future milestones. You may also click on milestones to see more detail and access links to the milestone's page.

Please use a JavaScript-enabled browser to view this element. Browse the result list directly.WEEKMONTHWashington, DC PAL notice issued2007-03-26T00:00:000Initial PAL notice issued
Washington, DC Project
March 26, 2007
Bethlehem Corps Letter of Deficiencies2007-04-30T00:00:000Maintenance deficiency notice issued
Bethlehem hydraulic system
April 30, 2007
Bethlehem Levee System PAL Agreement Due2007-04-30T00:00:000Levee owner response due
Bethlehem Project
April 30, 2007
Bethlehem hydraulic system/Initial PAL notice issued2007-06-22T00:00:000Initial PAL notice issued
Bethlehem hydraulic system
June 22, 2007
Bridgewater Levee System PAL Agreement Due2007-06-25T00:00:000Levee owner response due
Bridgewater System
June 25, 2007
Bethlehem maintenance deficiency correction period request2007-07-30T00:00:000Levee owner maintenance deficiency correction period request received
Bethlehem hydraulic system
July 30, 2007
Sunbury System Signed PAL Letter2007-08-16T00:00:000Levee owner PAL agreement received
Sunbury System
August 16, 2007
Bethlehem hydraulic system/Levee owner response due2007-09-22T00:00:000Levee owner response due
Bethlehem hydraulic system
September 22, 2007
State Hospital Levee PAL Signed2007-10-05T00:00:000Levee owner PAL agreement received
Danville Project
October 5, 2007
Richmond, VA Flood Protection Project PAL Signed2007-10-16T00:00:000Levee owner PAL agreement received
Norfolk Floodwall, VA Project
October 16, 2007
City of Richmond Returned Signed PAL Letter2007-10-18T00:00:000Levee owner PAL agreement received
Richmond Water Filtration Plant Project
October 18, 2007
Richmond, VA Flood Protection Project PAL Agreement Due2007-10-23T00:00:000Levee owner response due
Richmond, VA-Local Flood Protection Project
October 23, 2007
Sunbury System PAL Agreement Due2007-10-23T00:00:000Levee owner response due
Sunbury System
October 23, 2007
Washington, DC LFD postponement request2008-01-04T00:00:000Levee LFD postponement request received
Washington, DC Project
January 4, 2008
Washington, DC LFD postponement granted2008-01-11T00:00:000Levee LFD postponement period granted
Washington, DC Project
January 11, 2008
Maintenance deficiency data received2008-01-28T00:00:000Levee owner maintenance deficiency correction data received
Bethlehem hydraulic system
January 28, 2008
Spring Creek Levee PAL letter sent2008-02-06T00:00:000Initial PAL notice issued
Spring Creek Project
February 6, 2008
Left Bank Fourmile Run Levee System PAL Letter Sent2008-02-06T00:00:000Initial PAL notice issued
Four Mile Run Project
February 6, 2008
Norfolk Floodwall Levee System PAL Letter Sent2008-02-06T00:00:000Initial PAL notice issued
Norfolk Floodwall, VA Project
February 6, 2008
Howard Levee System PAL Letter Sent2008-02-06T00:00:000Initial PAL notice issued
Foster Joseph Sayers Project
February 6, 2008
Spring Creek Levee System PAL Letter Sent2008-02-06T00:00:000Initial PAL notice issued
Spring Creek Project
February 6, 2008
Left Bank of Codurus Creek Levee System PAL Letter Sent2008-03-31T00:00:000Initial PAL notice issued
York Project
March 31, 2008
Tyler Run Floodwall Levee System PAL Letter Sent2008-03-31T00:00:000Initial PAL notice issued
York Project
March 31, 2008
Spring Creek Levee PAL Signed2008-04-28T00:00:000Levee owner PAL agreement received
Spring Creek Project
April 28, 2008
Spring Creek Return Signed PAL Letter2008-04-28T00:00:000Levee owner PAL agreement received
Spring Creek Project
April 28, 2008
Bethlehem Levee System 1-Year Progress Report Due2008-04-30T00:00:000Levee owner progress report due
Bethlehem Project
April 30, 2008
Bethlehem maintenance deficiency correction data due2008-05-01T00:00:000Levee owner maintenance deficiency correction data due
Bethlehem hydraulic system
May 1, 2008
Left Bank Four Mile Run Levee System Signed PAL Letter Due2008-05-07T00:00:000Levee owner response due
Four Mile Run Project
May 7, 2008
Norfolk Floodwall Levee System Signed PAL Letter Due2008-05-07T00:00:000Levee owner response due
Norfolk Floodwall, VA Project
May 7, 2008
Right Bank Four Mile Run Levee System PAL Letter Sent2008-05-07T00:00:000Initial PAL notice issued
Four Mile Run Project
May 7, 2008
Spring Creek Levee PAL agreement due2008-05-07T00:00:000Levee owner response due
Spring Creek Project
May 7, 2008
Howard Levee System Signed PAL Letter Due2008-05-07T00:00:000Levee owner response due
Foster Joseph Sayers Project
May 7, 2008
Spring Creek Levee System Signed PAL Letter Due2008-05-07T00:00:000Levee owner response due
Spring Creek Project
May 7, 2008
Holiday2008-05-26T00:00:000Maintenance deficiency notice issued
Keane
May 26, 2008
South Petersburg Levee System PAL Letter Sent2008-06-20T00:00:000Initial PAL notice issued
Petersburg Project
June 20, 2008
North Moorefield Levee System PAL Letter Sent2008-06-20T00:00:000Initial PAL notice issued
Moorefield Project
June 20, 2008
South Moorefield Levee System PAL Letter Sent2008-06-20T00:00:000Initial PAL notice issued
Moorefield Project
June 20, 2008
East Bayard Levee System PAL Letter Sent2008-06-20T00:00:000Initial PAL notice issued
Bayard Project
June 20, 2008
West Bayard PAL Letter Sent2008-06-20T00:00:000Initial PAL notice issued
Bayard Project
June 20, 2008
North Petersburg Levee System PAL Letter Sent2008-06-20T00:00:000Initial PAL notice issued
Petersburg Project
June 20, 2008
PAL Letter Due Back from Community for the Left Bank of Cordurus Creek Levee2008-06-30T00:00:000Maintenance deficiency notice issued
York County
June 30, 2008
Left Bank of Codurus Creek Levee System Signed PAL Letter Due2008-06-30T00:00:000Levee owner response due
York Project
June 30, 2008
PAL Letter Due Back from Community for Tyler Run Floodwall2008-06-30T00:00:000Maintenance deficiency notice issued
York County
June 30, 2008
Tyler Run Floodwall Levee System Signed PAL Letter Due2008-06-30T00:00:000Levee owner response due
York Project
June 30, 2008
Howard Levee PAL Signed2008-07-07T00:00:000Levee owner PAL agreement received
Foster Joseph Sayers Project
July 7, 2008
Norfolk Floodwall PAL Signed2008-07-17T00:00:000Levee owner PAL agreement received
Norfolk Floodwall, VA Project
July 17, 2008
City of Norfolk Return Signed PAL Letter2008-07-17T00:00:000Levee owner PAL agreement received
Norfolk Floodwall, VA Project
July 17, 2008
Black Gut Levee System PAL letter sent2008-08-21T00:00:000Initial PAL notice issued
Black Gut Levee Project
August 21, 2008
South Moorefield Levee System PAL Signed2008-09-05T00:00:000Levee owner PAL agreement received
Moorefield Project
September 5, 2008
West Bayard Levee System PAL Signed2008-09-09T00:00:000Levee owner PAL agreement received
Bayard Project
September 9, 2008
Personal tools
Add levee records